Fields: Task History

Task History displays a list of the actions and results of the action on a specific scheduled task.

Scheduled Tasks > Manage this task group > View history

Task History List

Displays the actions that were performed, either automatically or manually, on the current task.

The list includes this information:

Option Description

Status

Displays the last reported state of the task.

Status Msg

Displays the last message sent regarding the task. You can use the Status Msg column to trouble shoot for problems with the task.

Start

Indicates the date and time when the action on the task was triggered.

End

Indicates the date and time when the action on the task either ended normally, was terminated, or was halted by an error.

Related topics